Preparation/Installation Overview
The following steps will assist the installer with a systematic approach for installing the
Quicklub Automated lube system on the Case Sprayer. By following the steps outlined, a
successful installation will be achieved and will increase the service life of all pins and bearings
connected to the lube system.
Preparation
Compare the bill of material with the kit contents
Clean machine thoroughly
Survey the equipment and locate all lubrication points to be serviced by the lubrication
system
Lubricate each point with a grease gun prior to removing grease fittings to assure grease
acceptance. Any points that will not accept grease must be repaired prior to system
installation.
After confirming all points will accept grease, remove all grease fittings.
Installation Overview
Install appropriate adapters and tube fittings in lube points.
Position valve mounting brackets on machine.
Attach metering valves to previously mounted brackets.
Using tubing cutters, cut to length individual tubing feed lines from secondary valves to lube
points and make connections.
When installing feed line tubing into the Quicklinc fittings, push until firmly seated.
Neatly bundle, loom with spiral wrap provided and tie strap feed lines wherever possible to
protect from abrasion.
Size, cut and attach appropriate hose ends to all supply lines. The high-pressure hose is
used as supply lines from the pump to the primary valve and the primary to the secondary
valves. It is recommended that the supply lines be routed and cut only after all valves and
the electric pump have been attached to the machine. This assures the supply line is cut to
the proper length. Also, allow for unrestricted movement while the machine is in motion.
Route supply lines from the pump to primary valve and from the primary valve to the
secondary valves and make connections.
Secure supply/feed lines with tie straps, so not in harms way.
Mount pump and make electrical connections (electrical diagram included with the pump).